Development Process
Timeline
Action |
Timeframe |
Customer initiates CISDE process |
Start |
CISDE team develops prototype |
1-4 weeks |
Customer reviews CISDE prototype |
2 business days |
CISDE team creates CBT draft |
3-12 weeks |
Customer and others provide final review |
2 business days |
CISDE team provides final CBT file |
5 business days |
Customer posts CBT in desired location |
Finish |
Timeline Guidelines
Timeline Guidelines: Prototype Development
Features |
Less than 10 minutes |
10 to 30 minutes |
30 minutes or more |
Standard CBT with all content developed |
Within 1 week |
Within 2 weeks |
Within 3 weeks |
Standard CBT with no content developed |
Within 2 weeks |
Within 3 weeks |
Within 4 weeks |
Timeline Guidelines: CBT Draft
Features |
Less than 10 minutes |
10 to 30 minutes |
30 minutes or more |
Standard CBT with all content developed |
3 weeks |
5 weeks |
7 weeks |
Standard CBT with no content developed |
5 weeks |
7 weeks |
9 weeks |
Options
- Voice Over
- Add an additional 2 weeks
- Knowledge Checks
- Add an additional 1 week
- Graded Assessment
- Add an additional 1 week
Notes
Customer should provide CISDE with the following details within 48 hours of request:
- Content to be included
- Targeted audience
- Who the subject matter experts are
- Who CISDE should contact if there are questions
- Names of all who will need to review before finalizing
- Formatting requirements (color scheme, logos, etc.)
- Where the document will live
Things that can slow the process:
- Delays in providing CISDE team with content or access to test system and/or resources
- Changes that occur to the process/content during CBT development
- Not meeting review deadlines for drafts
- A request involving a large amount of content
- A request involving extremely complex content